Customer Access Point, Stowmarket, closed
Due to unforeseen circumstances the Customer Access Point in Stowmarket is currently closed.
For any queries please phone Customer Services on 0300 123 4000 or visit one of our other Customer Access Points
A new version of the Lawshall Neighbourhood Development Plan (NDP) - the Lawshall NP Review - has been prepared by Lawshall Parish Council and local community to continue to help guide and shape future development in the parish. It covers the plan period 2021 - 2037 and now replaces the previously adopted plan.
In an 'Officer Decision' taken on Friday 19 April 2024, Babergh District Council agreed to adopt ('make') the Lawshall NP Review.
The following provide supporting evidence for the adopted plan:
The following statement confirmed our acceptance of the recommendations set in the Examiners Report:
Babergh District Council appointed Ann Skippers BSc (Hons) MRTPI FHEA FRSA AoU to carry out an independent examination of the Lawshall NDP Review. The examination included two focused consultation periods which were relevant to the basic condition tests. Details of those events are published further below.
On Thursday 22 February 2024, the Examiner issued her final report. It recommends that the Review Plan did not need to go back to a local referendum and that, subject to some additional modifications being made, the district council should 'make' (adopt) the plan.
In late December 2023, the Government published a new NPPF. This second focused consultation exercise was undertaken to allow for new comments to be made on the relevant basic condition test. The consultation period ran from 10 - 26 January 2024.
A copy of the consultation letter and all made representations is published below:
Following publication of a new NPPF (in Sept 2023), and the adoption of the Joint Local Plan Part 1 (in Nov 2023), we carried out a focused consultation exercise on whether or not these two events had implications for the Lawshall NP Review with regard to it meeting two of the basic condition tests. The consultation period ran from 27 November to 11 December 2023.
A copy of the consultation letter and all made representations are published below.
The NDP regulations required the relevant local planning authority to submit a statement to the examiner that sets out their assessment of the nature of the modifications being made to the NDP.
The submission draft Lawshall NP Review was published for public consultation between 2 August and 15 September 2023.
The Parish Council (the qualifying body) had formally submitted the following documents.
An assessment on how this Review Plan met the basic conditions formed part of examination. At the time of submission, our initial checks suggested that the relevant procedural requirements had been met. See our Regulation 15 Checklist.
Respondents were also reminded that their comments would be forwarded to the examiner and, with the exception of personal details, be published on this website.
The pre-submission draft plan was screened to determine whether a Strategic Environmental Assessment (SEA) and or a Habitats Assessment (HRA) were required. Both were 'screened-out'. The relevant reports and determination notices are published below:
Pre-submission consultation on the Review Plan ended on 30 November 2022.
With the exception of the area designation notice below, all other documents relating to the previously adopted Lawshall NDP (Oct 2017) have been archived from this webpage.